Generation

Choose your connection path

Our goal is to connect your generation project safely and efficiently. Use the tabs below to choose the path that best matches how your system will operate.

< 150 kW

Small microgeneration

For microgeneration projects under 150 kW designed to offset all or part of your home, farm or business electricity consumption. Common examples include residential solar and smaller farm or commercial rooftop systems.

  • Purpose: Your system should be sized to offset a portion of your annual on-site electricity use
  • Location: Your system must be installed on the property where electricity is used, or on an adjacent property that you own or lease
  • Connection capacity: FortisAlberta will confirm available capacity after you apply. Capacity is not guaranteed and may change.

Eligibility: FortisAlberta’s microgeneration processes comply with the Electric Utilities Act and the Micro-generation Regulation. Microgeneration allows consumers to offset a portion of their electricity use by generating electricity from renewable or alternative energy sources.

Important: FortisAlberta recommends that you do not purchase or install generation equipment until FortisAlberta has completed review and approval of your application.

PCS update: Certified power control systems may support export-limited or non-export configurations. A PCS Commissioning Record and fail-safe verification are required.

Aggregated sites: If the same customer submits multiple Small microgeneration applications, FortisAlberta may assess them together as one project. If the combined capacity is 150 kW or greater, the project may be subject to the Large microgeneration process.

Apply online: Submit and track your small microgeneration application through PowerClerk

Resources 18 resources
150 to 4999 kW

Large microgeneration

For larger microgeneration projects designed to offset a farm, commercial or industrial customer’s annual electricity consumption.

  • Purpose: Size the system to offset some or all of your annual on-site electricity use
  • Location: Install your system on the property where the electricity is used, or on an adjacent property that you own or lease

Project size: The maximum is the lesser of 4,999 kW or the customer service rating.

Eligibility: FortisAlberta’s microgeneration processes comply with the Electric Utilities Act and the Micro-generation Regulation. The intent of microgeneration is to allow consumers to offset a portion of their electricity use by generating electricity from renewable or alternative energy sources.

⚠️ Key Things to Know Before You Start

  • Important: FortisAlberta recommends that you do not purchase or install generation equipment until FortisAlberta has completed review and approval of your application and completed a detailed study review. After accepting the DLS and completing any necessary studies, confirm equipment requirements with your project team.
  • Available interconnection capacity is not guaranteed and may change over time as other projects connect to the electricity system or the conditions on the system change
  • All projects require engineering and technical reviews to ensure they can operate safely and reliably
Large microgeneration process at a glance
Stage 0Form A Intake

Submit the completed Form A and the supporting project information requested by FortisAlberta. The application is reviewed for completeness before the project advances.

Stage 1Capacity Check

FortisAlberta completes an initial capacity review and identifies possible feeder or system constraints. This check does not guarantee or reserve interconnection capacity.

Stage 2Detailed Level Study

The Detailed Level Study confirms interconnection requirements, required system modifications and any additional studies. After accepting the DLS and completing the identified studies, confirm equipment requirements with your project team.

Stage 3110-Day Package

Submit the engineering information and project documents identified for the 110-day milestone. Project-specific requirements are confirmed through the DLS and by the FortisAlberta project team.

Stage 430-Day Package

Submit the project information and documents identified for the 30-day milestone. Confirm the exact package requirements and due date with your FortisAlberta project contact.

Stage 5Commissioning Package

Provide the required commissioning documents, permits, inspection records and test results. Complete any project-specific commissioning and witnessing requirements before energization.

Stage 6Energization

FortisAlberta completes its final review and required metering work. Do not energize or export electricity until FortisAlberta provides the applicable written authorization.

Sample LMG project requirements (Gantt chart)

Use this sample schedule to understand the typical large microgeneration stages, submission milestones and project requirements. This timeline does not account for customer processing and submission of required information. Project timelines will extend accordingly. Actual timing and requirements are project-specific.

Resources 27 resources

DER bulletins and updates

DER Bulletin 2026-004

Technical standards and studies

DER-02 – Technical Interconnection Requirements for All Three-Phase DER and Single-Phase DER 150 kW and Greater DER-02A – FortisAlberta Engineering Study Requirements DER-02B – FortisAlberta Effective Grounding Study Requirements DER-02C – Fast Frequency Response and Contingency Reserve Requirements DER-02D – FortisAlberta ICAP Technical Requirements for DER 500 kVA and Greater DER-02E – FortisAlberta ICAP Process Requirements for DER 500 kVA and Greater DER-02F – FortisAlberta Model Validation Requirements

Commissioning and configuration

CCE List and Guidance DER Inverter Configuration Template

Getting started and process guides

Appendix C – Queue Management Practice Large microgeneration Presentation — February 2026 Large microgeneration Process Gantt Chart and Checklist LMG Interconnection Guide LMG Road Map

Applications and authorizations

Customer Cable Request Form Form A – Microgeneration Notice Third-Party Authorization – Microgeneration

Metering and ongoing operations

Maintenance Verification Report Sample – Maintenance Verification Report

Regulations and dispute forms

Alberta Microgeneration Regulation Alberta Utilities Commission (AUC) Website AUC Microgeneration Notice Submission Guideline IEEE 1547-2018 – Standard for Interconnection and Interoperability of Distributed Energy Resources IEEE 1547.1-2020 – Standard Conformance Test Procedures for DER Interconnection Equipment Notice of Complaint – Form C Notice of Dispute – Form B
Export & Non-Export Generation

Distributed & Commercial Generation

For commercial solar, wind, gas, storage and other projects that plan to export power onto the electrical system or operate in a non-export configuration and do not qualify as microgeneration.

  • Exporting generation projects
  • Battery energy storage systems
  • Combined heat and power
  • Projects that may require AUC, AESO or TFO coordination
Resources 35 resources

DER bulletins and updates

DER Bulletin 2026-004

Technical standards and studies

DER-01 - FortisAlberta Technical Interconnection Requirements for Single-Phase DERs Less than 150 kW DER-02 - FortisAlberta Technical Interconnection Requirements for All Three Phase DER and Single-Phase DER 150 kW and Greater DER-02A - FortisAlberta Engineering Study Requirements DER-02B - FortisAlberta Effective Grounding Study Requirements DER-02C FortisAlberta Fast Frequency Response and Contingency Reserve Requirements DER-02D - FortisAlberta ICAP Technical Requirements for DER 500 kVA and Greater DER-02E - FortisAlberta ICAP Process Requirements for DER 500 kVA and Greater DER-02F - FortisAlberta Model Validation Requirements

Commissioning and configuration

CCE List and Guidance As-Built Generator Parameters DER IFC Data Requirements V2 DER Inverter Configuration Template DER sample PQ data Interconnection Protection Settings & Commissioning (IPSC) Power Quality Benchmark Compliance - Template V1.3 Power Quality Compliance - Example V1.3

Getting started and process guides

Appendix A - Fee Schedule Appendix B - AESO Interconnection and FortisAlberta Appendix C - Queue Management Practice Customer Generator Options Table DER Interconnection Guide

Applications and authorizations

Customer Cable Request Form DER Pre-Application DLS Application (Download to complete the form) FortisAlberta - Customer Confirmation of Lands re AESO SASR Submission FortisAlberta - DER Interconnection Package Checklist HLS Application (Download to complete the form) Small-Scale Generation Application Third-Party Authorization Distributed Generation

Metering and ongoing operations

Maintenance Verification Report Option M - Distributed Generation Sample - Maintenance Verification Report

Regulations and dispute forms

Alberta 1547-2018: IEEE 1547-2018 Standard Adjustments for the Province of Alberta, Canada Section 101 Application Requirements
Distribution-connected supply

Small Scale & Community Generation

For distribution-connected projects that supply electricity to the grid from renewable or alternative sources.

  • Community Generation: Includes projects that provide locally generated electricity for the benefit of participating community members
  • Project size: Limited by distribution system capacity, typically up to 24 MW
Small scale generation projects require both a small-scale generation application and a high-level study application as part of the DG process.
Resources 35 resources

DER bulletins and updates

DER Bulletin 2026-004

Technical standards and studies

DER-01 - FortisAlberta Technical Interconnection Requirements for Single-Phase DERs Less than 150 kW DER-02 - FortisAlberta Technical Interconnection Requirements for All Three Phase DER and Single-Phase DER 150 kW and Greater DER-02A - FortisAlberta Engineering Study Requirements DER-02B - FortisAlberta Effective Grounding Study Requirements DER-02C FortisAlberta Fast Frequency Response and Contingency Reserve Requirements DER-02D - FortisAlberta ICAP Technical Requirements for DER 500 kVA and Greater DER-02E - FortisAlberta ICAP Process Requirements for DER 500 kVA and Greater DER-02F - FortisAlberta Model Validation Requirements

Commissioning and configuration

CCE List and Guidance As-Built Generator Parameters DER IFC Data Requirements V2 DER Inverter Configuration Template DER sample PQ data Interconnection Protection Settings & Commissioning (IPSC) Power Quality Benchmark Compliance - Template V1.3 Power Quality Compliance - Example V1.3

Getting started and process guides

Appendix A - Fee Schedule Appendix B - AESO Interconnection and FortisAlberta Appendix C - Queue Management Practice Customer Generator Options Table DER Interconnection Guide

Applications and authorizations

Customer Cable Request Form DER Pre-Application DLS Application (Download to complete the form) FortisAlberta - Customer Confirmation of Lands re AESO SASR Submission FortisAlberta - DER Interconnection Package Checklist HLS Application (Download to complete the form) Small-Scale Generation Application Third-Party Authorization Distributed Generation

Metering and ongoing operations

Maintenance Verification Report Option M - Distributed Generation Sample - Maintenance Verification Report

Regulations and dispute forms

Alberta 1547-2018: IEEE 1547-2018 Standard Adjustments for the Province of Alberta, Canada Section 101 Application Requirements
Backup power only

Standby generation

For battery backup, portable generators, GenerLinks, fixed standby generators and critical service generators that provide power during utility outages and are not intended to export.

Closed transition systems must parallel the utility system for less than 100 milliseconds. Systems that parallel for more than 100 ms require the Distributed Generation process.
Resources 1 resource

Complete resources library
All generation documents, organized by connection pathway.

Open complete resources library

Hosting capacity map

Explore the estimated generation capacity available on FortisAlberta distribution feeders to help inform early project planning.

View hosting capacity map

Need help choosing the right path?

FortisAlberta offers a pre-application consultation to provide information on the interconnection process. Contact FortisAlberta before submitting your application if you are unsure which process applies.

Small microgeneration: microgen@fortisalberta.com
Large microgeneration, distributed generation and standby: generation@fortisalberta.com